Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Primavera Risk Analysis, Build impacted plans

2 replies [Last post]
Alexandre Faulx-B...
User offline. Last seen 1 year 51 weeks ago. Offline
Joined: 20 Jan 2003
Posts: 1355

Hello Planners,

I am trying to build risk impacted plans (both pre- and post-mitigation); everything works fine, except that I cannot have the risk summary tasks to include the risk impact tasks together with the base task

for example: the base task is 10 day long and the risk impact task is 2 day long; in the post-mitigation plan, the risk summary task is only 10 day long and the risk impact task is scheduled after the end of the summary task

5241
1031.png

Both the base task and the risk summary task end on may 14; the risk impact task starts on may 15 and ends on may 14! does the error come from this point?

in the PRA tutorial, the picture page 46 shows both the base and the risk impact tasks within the risk summary task's duration

5240
1030.png

Thank you for helping,

Alexandre

Replies

Santosh Bhat
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

It behaves correctly during the Actual analysis iterations. Was this the solution?