Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

NEC3 Risk Register

6 replies [Last post]
Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hello Everyone

This is a sort of mini survey.

I would like to ascertain whether the NEC3 requirement for a risk register is actually implemented in the real world.

If any one has been involved in NEC3 projects how many had a risk register established and how many not?

No details please just the numbers.

Thank you in advance.

Mike Testro

Replies

alex sobhi
User offline. Last seen 13 years 4 weeks ago. Offline
Joined: 28 Mar 2011
Posts: 2
Groups: None

 

hello everyone, 

I am a student at Univeristy College London. My dissertation is examining the use of risk register on NEC3 contracts. I would greatly appreciate it if one of you can send me an example of a risk register which has been implemented on a real life NEC contract which you have worked on. My email is alexsobhi8@hotmail.com. Or Perhaps you could tell me a bit more about your experiences via email, as I will be needing to interview some people over the phone

Kind regards and thanks for effort,

A.Sobhi

Gary Whitehead
User offline. Last seen 4 years 46 weeks ago. Offline

Currently working on a suite of around a dozen projects under modified NEC, and all have risk regsiters tracking both cost and schedule risks, with identified mitigation plans, and that feed into forecast cost and completion estimates, using Pertmaster to run the analysis and a programme Risk Manager to oversee the process. We're barely into the implementation phase on the earliest projects, so it remains to be seen how often the register is reviewed and how well it is used as a project management tool.

 

Previosuly, I worked on 2 NEC contracts. Both had (cost) risk registers agreed at contract signature, both were only looked at afterwards to assess CEs.

 

Cheers,

 

G

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None

Oliver,

I agree with your comments about people not realising the amount of resources required to administer a NEC contract but I think everyones attitude plays just as big, (if not bigger), role.

There's still a big "wait and see what happens" attitude out there when dealing with problems rather than a "sort it as you go" approach.

The written word of the contract has good intentions but the people reading and implementing those words let it down.

But maybe that can be said about many contracts, the deal struck between the parties is forgotten or misadministered as other seemingly more pressing and important needs are encountered.

Oliver Melling
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine

Mike,

Almost all the projects im involved with have costed risk registers on them.  Although, I dont think they are used as effectively as they are supposed to be, more updated as a requirement than used as a tool.

I think Andrew is right about Mr.Ed and his beverage. Most contracts i come across are based on NEC3, but usually the client isnt aware (or chooses to negate) their part to play as 'the client' with regard to acceptance periods, acceptance of variations etc. I think its because most people dont have/dont realise the amount of resource required to administer an NEC3 form of contract correctly. This is kind of its flaw, as how do you show the ROI of the additional admin required on NEC3 contracts?

It would be the comparison of additional admin costs against the cost of court fees and delay consultancy you never ended up having to pay?!

Mike Testro
User offline. Last seen 5 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Andy

Thank you for your response - I have not had much exposure to NEC3 - only about 3 cases so far and I have never been involved in running a project under it.

I thought the Risk Register would be set up and then abandoned.

As you said something on the lines of "You can lead a whore to culture - but you can't make her think"

Best regards

Mike Testro

Andrew Flowerdew
User offline. Last seen 2 years 23 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None

Mike,

Nearly all of the NEC3 contracts I've been involved with have had a risk register established, (usually at tender), but how many have used it effectively and how many have put it in the bottom drawer and forgotten about it would be telling.

The saying that springs to mind when talking about NEC contracts is the one concerning something about a horse and water , you might know the one!!!!

Regards,

Andy