Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Importing 3 Point Estimates into Pertmaster

No replies
Dave Jones
User offline. Last seen 10 years 41 weeks ago. Offline
Joined: 4 Sep 2009
Posts: 11
Groups: None
I am using the latest versions of P6 and Primavera Risk Analysis 8.6 (formerly Pertmaster).

For each resource assignment, I have a 3 point estimate for the effort .. ie min 6 hrs, likely 12 hrs, max 23 hrs.

There are multiple resource assignments per activity.

How cam I import this data into Pertmaster?

The standard Primavera/Pertmaster integration only allows either:
a) resources to be imported (but no 3 point estimates), or
b) summarised costs with 3 point estimates at the activity level.

Could a Macro importing from an excel file be a possibility? Or are there any other options?