Delay Calculation and Resources Availability

Hi,

I had a telephonic interview. The interviewer asked me three questions. I replied all and alhamdulillah he was satisfied, but I want the an experienced reply from you guys, the question were these;

Q1- you have a project of 12 months, at the mid of the project i.e. 6 months you find the project is 2 months behind the schedule. The management asks you to prepare a recovery plan. What you do (the procedure of the recovery plan)

Q2- you have a labor histogram of 0 to 100 labor units. The management restricts you to 50% usage of the available resources. What negative effect(s) that restriction would put on the project?

Q3- at some event in the project you prepare a report for the management, and find that the project is behind the schedule, the actual progress is less then the planned prgress. How would you calculate that we are behind the schedule?

Thanx

M
Mike Testro 👤 Member for 20 years 5 months

Hi Tanveer

a) Adjust the logic - work patterns - resources within reasonable limits.

b) Following a resource levelling excercise the project will probably take longer to complete.

c) Reschedule the project

All of the above depends on the quality of your programme.

If you have any artificial constraints - FF SS Links - Lead lags - Top down scheduling - then you will get a false result.

Best regards

Mike Testro

Forum Sponsor

Top Posters

anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
Soheil Barekat
4 posts