Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

EPC

4 replies [Last post]
Abhiyan Arvind Sheth
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 23 May 2010
Posts: 9

Hi..

 

Can someone elaborate on Sulfur Recovery Unit commissioning sequence?

 

Abhiyan

Replies

Abhiyan Arvind Sheth
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 23 May 2010
Posts: 9

Thanks Mike.

 

Abhiyan

Abhiyan Arvind Sheth
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 23 May 2010
Posts: 9

Thanks Mike.

 

Abhiyan

Abhiyan Arvind Sheth
User offline. Last seen 1 year 48 weeks ago. Offline
Joined: 23 May 2010
Posts: 9

Thanks Mike.

 

Do you know what is EOT, & what is EQT?

 

Abhiyan

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Abhiyan

There is nothing special about a programme for an EPC contract.

Every programme should have a design development section leading into procurement and construction - even if the design is being provided by the Employer.

Best regards