Hello Everybody,
Good day! Please I need your input and suggestions. I am from consulting side and I need to check, monitor and comments the Weekly & Monthly Progress Report of the contractors and their accomplishment based on actual.
The type of project is a Marine Works. Scope of Works are as follows:
1. Construction of Piers using Caisson Method.
2. Construction of Dry Dock 1 & 2 and Quay 1 & 2.
3. Sill & Apron
4. Electro Mechanical
5. Building and Storage Areas
In order to monitor their current programme against baseline, aside from basic comments such as, delays, floats, sequence, critical activities so on & so forth. What are the other related and relevant interesting topics that I can discuss during the weekly and monthly progress meeting with regards to their schedule/programme?
Any comments and suggestion is highly appreciated.
Thanks in advance.
Regards.
Replies