Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

approval of clause 14

5 replies [Last post]
G. kumar
User offline. Last seen 6 years 39 weeks ago. Offline
Joined: 1 Jul 2004
Posts: 9
Groups: None
Hai all,
A clause 14 program is submitted and not approved by the consultant after 4 months. Meanwhile the trial trench work has been completed by the contractor and could find that the water pipeline is too close and hence to be diverted before piling work. And now the contractors piling work for bridges is getting delayed due to diversion work of pipeline. But the consultant is telling the clause 14 is not approved and can not approve any variation or cost impact. Who is correct? Please advice

Regards,
G.Kumar

Replies

Abdelmoneim Youss...
User offline. Last seen 8 years 33 weeks ago. Offline
Joined: 24 Oct 2004
Posts: 21
Variation order means change in scope of work you can claim with cost and time with or without approved programm
A D
User offline. Last seen 3 years 23 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Thats true trevor, but there must be some condition in the contract or time-line specified in the contract to approve/comment on the program.

To do a variation work, contractor must have received PMI/EI to proceed. The variation cost and time can be settled later on as well, as and when u receive approval of Clause 14 program.

Anyway, do u really think consultant need a incentive.

Cheers,

Ravi
Trevor Rabey
User offline. Last seen 1 year 22 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None
It is in the contractor’s interest to submit the program on time and make it as good as possible so that it will get approved and can be used for EOTs, Variations etc.

But it is the client’s interests for the consultant to withold approval forever, no matter how good the program is so that there can never be any consideration of EOTs, Variations etc.

Where is the incentive for the consultant to approve?
There’s nothing in it for the client.
Abdelmoneim Youss...
User offline. Last seen 8 years 33 weeks ago. Offline
Joined: 24 Oct 2004
Posts: 21
Activities that had been done it consider as build time schedule , and according RFI and some documents like submittals of material,shopdrwaings approval we can decide the responsible for delay .

But Variation should be apprved other wise the owner should change the consultant or find Project management consultant for the project
Charleston-Joseph...
User offline. Last seen 2 years 39 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Please give additional information.

Let say the contractor submitted the clause 14 program, then the consultant commented, then the contractor again submitted taking into consideration the consultant comment, and so on and so on and so forth.

Did the consultant whimsically defer the approval of the clause 14 program????

Is the contractor working on the submitted clause 14 program, while the said clause 14 program is under review????

Give us the true and honest picture in this way, you will get the best advice.