Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WORK BREAKDOWN STRUCTURE ( LEVEL 3 PROGRAM)

6 replies [Last post]
Milind Pandhare
User offline. Last seen 8 years 6 weeks ago. Offline
Joined: 29 Aug 2005
Posts: 54
Groups: None



-----WORK BREAKDOWN STRUCTURE-----

Structure: xxx.xx.xx.xx.xx.xx.xx.xx

WBS Code Title

.
B55 B + G + 7 + H C R E S I ( B - 5 5 )
BO1 RESI. BLDG.PROJECT
BO1.1 KEY MILESTONE
BO1.2 Submittals & Approvel
BO1.2 .1 Subcontractor
BO1.2 .2 Shopdrawing
BO1.2 .3 Nominated supplier / Subcontractor
BO1.2 .4 Provisional Sum Finilise By Client
BO1.4 CONSTRUCTION
BO1.4 .1 Mobilisation
BO1.4 .2 Sub Structure
BO1.4 .2 .1 Shoring Piling
BO1.4 .2 .2 Excavation
BO1.4 .2 .3 Dewatering
BO1.4 .2 .4 Raft Work
BO1.4 .2 .4 .1 PCC & Waterproffing
BO1.4 .2 .4 .2 Rebar
BO1.4 .2 .4 .3 MEP work
BO1.4 .2 .4 .4 Concreting
BO1.4 .2 .5 Basement Level
BO1.4 .2 .5 .1 Column
BO1.4 .2 .5 .1 .1 Rebar
BO1.4 .2 .5 .1 .2 Form Work
BO1.4 .2 .5 .1 .3 Concreting
BO1.4 .2 .5 .2 Shear Wall
BO1.4 .2 .5 .2 .1 Rebar
BO1.4 .2 .5 .2 .2 Form Work
BO1.4 .2 .5 .2 .3 Concreting
BO1.4 .2 .5 .3 Slab
BO1.4 .2 .5 .3 .1 Rebar
BO1.4 .2 .5 .3 .2 Form Work
BO1.4 .2 .5 .3 .3 Conreting
BO1.4 .3 Super Structure
BO1.4 .3 .1 Ground Floor Level
BO1.4 .3 .1 .A Slab Work
BO1.4 .3 .1 .A . 1 Column
BO1.4 .3 .1 .A . 1.1 Rebar
BO1.4 .3 .1 .A . 1.2 Form Work
BO1.4 .3 .1 .A . 1.3 Concreting
BO1.4 .3 .1 .A .2 Sherar Wall
BO1.4 .3 .1 .A .2 .1 Rebar
BO1.4 .3 .1 .A .2 .2 Form Work
BO1.4 .3 .1 .A .2 .3 Concreting
BO1.4 .3 .1 .A .3 Slab
BO1.4 .3 .1 .A .3 .1 Form Work
BO1.4 .3 .1 .A .3 .2 Rebar
BO1.4 .3 .1 .A .3 .3 MEP Work
BO1.4 .3 .1 .A .3 .4 Concreting
BO1.4 .3 .2 First Floor Level
BO1.4 .3 .2 .A Slab Work
BO1.4 .3 .2 .A .1 Column
BO1.4 .3 .2 .A .1 .1 Rebar
BO1.4 .3 .2 .A .1 .2 Form Work
BO1.4 .3 .2 .A .1 .3 Concreting
BO1.4 .3 .2 .A .2 Shear Wall
BO1.4 .3 .2 .A .2 .1 Rebar
BO1.4 .3 .2 .A .2 .2 Form Work
BO1.4 .3 .2 .A .2 .3 Concreting
BO1.4 .3 .2 .A .3 Slab
BO1.4 .3 .2 .A .3 .1 Form Work
BO1.4 .3 .2 .A .3 .2 Rebar
BO1.4 .3 .2 .A .3 .3 MEP Work
BO1.4 .3 .2 .A .3 .4 Concreting
BO1.4 .3 .3 Second Floor Level
BO1.4 .3 .3 .A Slab Work
BO1.4 .3 .3 .A .1 Column
BO1.4 .3 .3 .A .2 Shear Wall
BO1.4 .3 .3 .A .3 Slab
BO1.4 .3 .3 .B Part 2
BO1.4 .3 .3 .B .1 Column
BO1.4 .3 .3 .B .2 Shear Wall
BO1.4 .3 .3 .B .3 Slab
BO1.4 .3 .4 Third Floor Level
BO1.4 .3 .4 .A Part 1
BO1.4 .3 .4 .A .1 Column
BO1.4 .3 .4 .A .2 Shear Wall
BO1.4 .3 .4 .A .3 Slab
BO1.4 .3 .4 .B Part 2
BO1.4 .3 .4 .B .1 Column
BO1.4 .3 .4 .B .2 Shear Wall
BO1.4 .3 .4 .B .3 Slab
BO1.4 .3 .5 Fifth Floor
BO1.4 .3 .5 .A Part 1
BO1.4 .3 .5 .A .1 Column
BO1.4 .3 .5 .A .2 Shear Wall
BO1.4 .3 .5 .A .3 Slab
BO1.4 .3 .5 .B Part 2

--------------------------------------------------------------------------------
PRIMAVERA PROJECT PLANNER

Date 30OCT05 -----WORK BREAKDOWN STRUCTURE----- Page 2

MLD1 - RESI BLDG PROJECT
--------------------------------------------------------------------------------
BO1.4 .3 .5 .B .1 Column
BO1.4 .3 .5 .B .2 Shear Wall
BO1.4 .3 .5 .B .3 Concreting
BO1.4 .3 .6 Sixth Floor
BO1.4 .3 .6 .A Part 1
BO1.4 .3 .6 .A .1 Column
BO1.4 .3 .6 .A .2 Shear Wall
BO1.4 .3 .6 .A .3 Slab
BO1.4 .3 .6 .B Part 2
BO1.4 .3 .6 .B .1 Column
BO1.4 .3 .6 .B .2 Shear Wall
BO1.4 .3 .6 .B .3 Slab
BO1.4 .3 .7 Seventh Floor
BO1.4 .3 .7 .A Part 1
BO1.4 .3 .7 .A .1 Column
BO1.4 .3 .7 .A .2 Shear Wall
BO1.4 .3 .7 .A .3 Slab
BO1.4 .3 .7 .B Part 2
BO1.4 .3 .7 .B .1 Column
BO1.4 .3 .7 .B .2 Shear Wall
BO1.4 .3 .7 .B .3 Slab
BO1.4 .3 .8 Roof Floor
BO1.4 .3 .8 .1 Column
BO1.4 .3 .8 .1 .1 Rebar
BO1.4 .3 .8 .1 .2 Form Work
BO1.4 .3 .8 .1 .3 Concreting
BO1.4 .3 .8 .2 Shear Wall
BO1.4 .3 .8 .2 .1 Rebar
BO1.4 .3 .8 .2 .2 Form Work
BO1.4 .3 .8 .2 .3 Concreting
BO1.4 .3 .8 .3 Slab
BO1.4 .3 .8 .3 .1 Form Work
BO1.4 .3 .8 .3 .2 Rebar
BO1.4 .3 .8 .3 .3 MEP Work
BO1.4 .3 .8 .3 .4 Concreting
BO1.4 .3 .9 Upper Roof Floor
BO1.4 .3 .9 .1 Column
BO1.4 .3 .9 .1 .1 Rebar
BO1.4 .3 .9 .1 .2 Form Work
BO1.4 .3 .9 .1 .3 Concreting
BO1.4 .3 .9 .2 Shear Wall
BO1.4 .3 .9 .2 .1 Rebar
BO1.4 .3 .9 .2 .2 Form Work
BO1.4 .3 .9 .2 .3 Concreting
BO1.4 .3 .9 .3 Slab
BO1.4 .3 .9 .3 .1 Form Work
BO1.4 .3 .9 .3 .2 Rebar
BO1.4 .3 .9 .3 .3 MEP Work
BO1.4 .3 .9 .3 .4 Concreting
BO1.4 .4 Mep Work
BO1.4 .4 .1 Electrial work
BO1.4 .4 .1 .1 Basement Level
BO1.4 .4 .1 .1 .1 1st Fix
BO1.4 .4 .1 .1 .2 2nd Fix
BO1.4 .4 .1 .1 .3 Final FIx
BO1.4 .4 .1 .2 Ground Floor Level
BO1.4 .4 .1 .2 .1 1st Fix
BO1.4 .4 .1 .2 .2 2nd Fix
BO1.4 .4 .1 .2 .3 Final FIx
BO1.4 .4 .1 .3 First Floor Level
BO1.4 .4 .1 .3 .1 1st Fix
BO1.4 .4 .1 .3 .2 2nd Fix
BO1.4 .4 .1 .3 .3 Final FIx
BO1.4 .4 .1 .4 Roof Level
BO1.4 .4 .1 .4 .1 1st Fix
BO1.4 .4 .1 .4 .2 2nd Fix
BO1.4 .4 .1 .4 .3 Final FIx
BO1.4 .4 .2 Plumbing & Drainage
BO1.4 .4 .2 .1 Basement Level
BO1.4 .4 .2 .1 .1 1st Fix
BO1.4 .4 .2 .1 .2 2nd Fix
BO1.4 .4 .2 .1 .3 Final FIx
BO1.4 .4 .2 .2 Ground Floor Level
BO1.4 .4 .2 .2 .1 1st Fix
BO1.4 .4 .2 .2 .2 2nd Fix
BO1.4 .4 .2 .2 .3 Final FIx
BO1.4 .4 .2 .3 First Floor Level
BO1.4 .4 .2 .3 .1 1st Fix
BO1.4 .4 .2 .3 .2 2nd Fix
BO1.4 .4 .2 .3 .3 Final FIx
BO1.4 .4 .2 .4 Roof Level
BO1.4 .4 .2 .4 .1 1st Fix
BO1.4 .4 .2 .4 .2 2nd Fix
BO1.4 .4 .2 .4 .3 Final FIx
BO1.4 .4 .3 A/C Work
BO1.4 .4 .3 .1 Basement Level
BO1.4 .4 .3 .1 .1 1st Fix
BO1.4 .4 .3 .1 .2 2nd Fix
BO1.4 .4 .3 .1 .3 Final FIx
BO1.4 .4 .3 .2 Ground Floor Level
BO1.4 .4 .3 .2 .1 1st Fix
BO1.4 .4 .3 .2 .2 2nd Fix
BO1.4 .4 .3 .2 .3 Final FIx

BO1.4 .4 .3 .3 First Floor Level
BO1.4 .4 .3 .3 .1 1st Fix
BO1.4 .4 .3 .3 .2 2nd Fix
BO1.4 .4 .3 .3 .3 Final FIx
BO1.4 .4 .3 .4 Roof Level
BO1.4 .4 .3 .4 .1 1st Fix
BO1.4 .4 .3 .4 .2 2nd Fix
BO1.4 .4 .3 .4 .3 Final FIx
BO1.4 .4 .4 Fire Alarm Work
BO1.4 .4 .4 .1 Basement Level
BO1.4 .4 .4 .1 .1 1st Fix
BO1.4 .4 .4 .1 .2 2nd Fix
BO1.4 .4 .4 .1 .3 Final FIx
BO1.4 .4 .4 .2 Ground Floor Level
BO1.4 .4 .4 .2 .1 1st Fix
BO1.4 .4 .4 .2 .2 2nd Fix
BO1.4 .4 .4 .2 .3 Final FIx
BO1.4 .4 .4 .3 First Floor Level
BO1.4 .4 .4 .3 .1 1st Fix
BO1.4 .4 .4 .3 .2 2nd Fix
BO1.4 .4 .4 .3 .3 Final FIx
BO1.4 .4 .4 .4 Roof Level
BO1.4 .4 .4 .4 .1 1st Fix
BO1.4 .4 .4 .4 .2 2nd Fix
BO1.4 .4 .4 .4 .3 Final FIx
BO1.4 .5 Finishing Work
BO1.4 .5 .1 Basement Floor
BO1.4 .5 .1 .A Block work & Plaster
BO1.4 .5 .1 .B Water proffing & Flooring
BO1.4 .5 .1 .B .1 Wet Area
BO1.4 .5 .1 .B .2 Dry Area
BO1.4 .5 .1 .B .3 Other Area FLooring
BO1.4 .5 .1 .C False Ceiling
BO1.4 .5 .1 .C .1 1st Fix
BO1.4 .5 .1 .C .2 2nd Fix
BO1.4 .5 .1 .D Painting Work
BO1.4 .5 .2 Ground Floor
BO1.4 .5 .2 .1 Substation Work
BO1.4 .5 .2 .A Block work & Plaster
BO1.4 .5 .2 .B Water proffing & Flooring
BO1.4 .5 .2 .B .1 Wet Area
BO1.4 .5 .2 .B .2 Dry Area
BO1.4 .5 .2 .B .3 Other Area FLooring
BO1.4 .5 .2 .C False Ceiling
BO1.4 .5 .2 .C .1 1st Fix
BO1.4 .5 .2 .C .2 2nd Fix
BO1.4 .5 .2 .D Painting Work
BO1.4 .5 .3 First Floor
BO1.4 .5 .3 .A Block work & Plaster
BO1.4 .5 .3 .B Water proffing & Flooring
BO1.4 .5 .3 .B .1 Wet Area
BO1.4 .5 .3 .B .2 Dry Area
BO1.4 .5 .3 .B .3 Other Area FLooring
BO1.4 .5 .3 .C False Ceiling
BO1.4 .5 .3 .C .1 1st Fix
BO1.4 .5 .3 .C .2 2nd Fix
BO1.4 .5 .3 .D Painting Work
BO1.4 .5 .4 Roof Floor
BO1.4 .5 .4 .A Block work & Plaster
BO1.4 .5 .4 .B Water proffing & Flooring
BO1.4 .5 .4 .B .1 Wet Area
BO1.4 .5 .4 .B .2 Dry Area
BO1.4 .5 .4 .B .3 Other Area FLooring
BO1.4 .5 .4 .C False Ceiling
BO1.4 .5 .4 .C .1 1st Fix
BO1.4 .5 .4 .C .2 2nd Fix
BO1.4 .5 .4 .D Painting Work
BO1.4 .51 Carpentry & Joinery Work
BO1.4 .51.A Basement Floor
BO1.4 .51.B Ground Floor
BO1.4 .51.C First Floor
BO1.4 .51.D Roof Floor
BO1.4 .52 Internal Decoration Work
BO1.4 .52.A Basement Floor
BO1.4 .52.B Ground Floor
BO1.4 .52.C First Floor
BO1.4 .52.D Roof Floor
BO1.4 .6 External Work
BO1.4 .6 .1 Elevation -A
BO1.4 .6 .2 Elevation -B
BO1.4 .6 .3 Elevation -C
BO1.4 .6 .4 Elevation -D
BO1.4 .6 .E Other Work
BO1.4 .6 .E .1 Paving Work
BO1.4 .6 .E .2 External Painting
BO1.4 .7 Other Subcontractors Work
BO1.4 .7 .1 Metal Work
BO1.4 .7 .2 Other Provisional Item Work
BO1.4 .8 Demobilisation & Site Cleaning

Replies

Charleston-Joseph...
User offline. Last seen 2 years 38 weeks ago. Offline
Joined: 10 Jul 2005
Posts: 1347
Groups: None
Millind,

Your structure is showing level 8.

You need to summarize into level 3.

Just go to format, summarize, level 3 (using P3)

Cheers
Alex Wong
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
If the original post to impress us, it definitely created some attentions here.

:)
Alex
Christian Adrian ...
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 3 Jun 2003
Posts: 193
Groups: None
Millind

Kindly enlighten us on what you want to say in this thread...

Cheers!

Christian
Sen Moc
User offline. Last seen 18 years 15 weeks ago. Offline
Joined: 30 Aug 2005
Posts: 123
I think the originator just want to share a sample Level 3 WBS.
Alex Wong
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
No Idea!!!

I think some of the original post is missing

Alex
Clive Randall
User offline. Last seen 16 years 17 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 744
Groups: None
Im sorry what is the question here???