What do i do with critical path activities in a schedule
critical Path
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
The critical path is an important part of your programme, as it tells you which path is driving your end date. If any of these tasks are late, it will affect your completion date. However, I have had clients who simply don't want to see it. All they want is green! If you want to hide the critical path, press F9 to bring up the Schedule prompt. Go to options and under 'Define critical elements as', select 'Total Float less than or equal to'. In the field type -0.1h exit options and Click 'Schedule'.