Identifying Activities That Do Not Exist In The Primavera P6 Project Baseline

1 reply [Last post]
Emily Foster
User offline. Last seen 1 year 45 weeks ago. Offline
Joined: 19 Aug 2011
Posts: 625
Groups: None

Hi Guys,

Here's an article showing how to identifying activities that do not exist in the Primavera P6 project baseline http://ow.ly/gTkZf

Emily

Replies

Mike Testro
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Emily

Quite a convoluted exercise.

Just copy and paste the task names & UID to columns in a spreadsheet and compare the two lists.

If it was a Lotus 123 spread sheet then the baseline duplicates can be stripped out of the other database on a few clicks.

Best regards

Mike Testro