Deal all:
I'd like to know if a baseline programme can have actual progress data ? because sometimes with a complicated ongoing project,we need to update the baseline programme,i.e adding some milestones/activities ,adjusting or revising some relationships / duration / start and finish date and so on.
If the project have been carried out for about 50%(actual progress) and we have updated the baseline programme on base of the old BLP , what i presume is that i have to input all the actual data once more time, that'd be a huge work if the number of activities is as many as 1000 or even more.
My question is that can i revise the data on base of the actual progress schedule and then assign a new BLP which include the actual progress data ? Is there anyone having experience about this issue.
Thanks in advance and take this opportunity to Wish all of you Merry Christmas and Happy New Year.
Shiguo
Replies