Hello
Recently moved to high level planning in Months & Quarter duration. Scary as I have come from Hourly Planning!!
I remember from P3 traning years ago that you can create a Global Change, probably with a Text Field Column to show Days into Months? Something like :
Original Duration / 30 = No of Months
Can someone tell me the Global Change Data should run in P6 please?
Thanks
Laura
Hi Laura,
Try to provide separate 2 Text Column outside or beside OD column containing "Days" copied from OD & "Months" from there you formulate it using Global Change from Original Duration/30 and you'll see the result.
OD- Original Duration.
Thanks.
Thanks Raymund for your amazingly quick response.
I did do that one too.
You think away to show 2 columns? Months & Days?
Laura,
Global Change is not needed to show durations into Months.
Go to User Preferences... Time Units... Durations Format.. set Unit of Time to Months
Hope this will help.