Global Change to show Days as Month Duration>

3 replies [Last post]
Laura Vass
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 16 May 2012
Posts: 7
Groups: None

Hello

Recently moved to high level planning in Months & Quarter duration. Scary as I have come from Hourly Planning!!

I remember from P3 traning years ago that you can create a Global Change, probably with a Text Field Column to show Days into Months? Something like :

Original Duration / 30 = No of Months

 

Can someone tell me the Global Change Data should run in P6 please?

 

Thanks

 

Laura

Replies

Aldrin Morallos
User offline. Last seen 5 years 40 weeks ago. Offline
Joined: 1 Jun 2011
Posts: 5
Groups: None

Hi Laura,

 

Try to provide separate 2 Text Column outside or beside OD column containing "Days" copied from OD & "Months" from there you formulate it using Global Change from Original Duration/30 and you'll see the result.

 

OD- Original Duration.

 

Thanks.

Laura Vass
User offline. Last seen 11 years 48 weeks ago. Offline
Joined: 16 May 2012
Posts: 7
Groups: None

Thanks Raymund for your amazingly quick response.

I did do that one too.

You think away to show 2 columns? Months & Days?

Raymund de Laza
User offline. Last seen 31 weeks 4 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Laura,

Global Change is not needed to show durations into Months.

Go to User Preferences... Time Units... Durations Format.. set Unit of Time to Months

 

Hope this will help.