P6 Dosn't consider the highest TF

2 replies [Last post]
Jenny Ingco
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All Planners,

Why P6 dosent consider the highest TF in the schedule as the project TF? Seee the example below why P6 not consider teh -67 as the highest TF?

Total   -45

WBS1  -45

WBS2  -67

Thank you for any help,

Regars,

HANSON

Replies

Jenny Ingco
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Got it.. Thanks a lot Ron..

Ron Beechey
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 13 Jun 2002
Posts: 61

Hanson

Are you really looking at a TF or negative 45 and negative 67 and if that is true then -45 is higher than -67 (closer to zero)    Surely you don't have a -67 day total float in your schedule as that is indicating that you would over run your completion date that is showing in the schedule currently by 67 days

 

Ron