Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Planned&Actual %complete

No replies
Jenny Ingco
User offline. Last seen 2 years 29 weeks ago. Offline
Joined: 9 Jan 2012
Posts: 116

Dear All Planners,

 

I know the Actual % Complete in P6 = Physical % complete... But what I don't know how we can calculculate the Planned % complete for the same schedule? What is the procedure..

Thank you for any help..

 

Hanson