Multiple Critical Path

7 replies [Last post]
Henry Chiu
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 15 Jul 2011
Posts: 22
Groups: None

Dear Planners,

Client keeps on sending letter to our company regarding our schedule. Client illustrated multiple critical paths from our schedule. Is there any filter and or option in P6 to produce multiple critical paths. I have tried the Floath Path Order - but this is not in line with the activities identified in the clients letter. Any other option or any enhancements required.

Thanks

 

Henry

 

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

group by total float then filter for the groupings with the 3 lowest values 

Khuong Do
User offline. Last seen 2 years 3 weeks ago. Offline
Joined: 22 Feb 2010
Posts: 118
Groups: None
Hi,I wrote an article regarding How to display Multiple Critical path in Primavera P6.If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/07/07/how-to-display-multiple-critical-path-in-primavera-p6/
Henry Chiu
User offline. Last seen 10 years 46 weeks ago. Offline
Joined: 15 Jul 2011
Posts: 22
Groups: None

Ryan,

Client identified as "First Critical Path" Second Critical Path, Third Critical Path and Fourth Critical Path. In identifiying these activities there must be a built in filter option in the P6 program that will enable to produce the grouping of these activities. Client Scheduler is well versed in P6, and is always attacking on this particular issue. I just recently use P6.

 

Thanks

Henry

Ryan Lytollis
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 13 Nov 2011
Posts: 14

Henry,

 

I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

Ryan Lytollis
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 13 Nov 2011
Posts: 14

Henry,

 

I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

Ryan Lytollis
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 13 Nov 2011
Posts: 14

Henry,

 

I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?

Ryan Lytollis
User offline. Last seen 10 years 40 weeks ago. Offline
Joined: 13 Nov 2011
Posts: 14

Henry,

 

I am only aware of the multi-float paths which is set up in the advanced scheduling tap, are your clients selecting activities and saying they are critical to the project?