Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Summarized PLanned & Actual % are showing above 100% i.e. 652 % & 546% in P6

4 replies [Last post]
Ameen Pasha
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 21

Awaiting your positive responses with referencce to above mentioned subject "Summarized PLanned & Actual % are showing above 100% i.e. 652 % & 546% in P6 .1 after updation.

What is the reason, how to mitigate the issue.

 

998
p6.1.jpg

Ameen N. Pasha.

Replies

Ameen Pasha
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 21

Thanks issue resolved.

Muhammad Anjum
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 21 Mar 2012
Posts: 8
Groups: None

Before data date you can not assign any planned date to any activity or milestone. You will have to assign actual finish to finish milestone as 26th Nov.2011.

Muhammad Anjum
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 21 Mar 2012
Posts: 8
Groups: None

What is basis of progress calculation? Manhours or Quantities or something else?

 

Muhammad Anjum

Ameen Pasha
User offline. Last seen 10 years 11 weeks ago. Offline
Joined: 17 Jun 2008
Posts: 21

How to add constriant to finish milestone , which is before data date example an finish milestone currently having date of 28th march 2012 to constraint - must finish on or before 26th november 2011.

p6.1 is not accepting.

Please provide your exdpertise to solve the issue.

Thanks in advance.

 

Ameen N. Pasha.