Doing new P6 planning

2 replies [Last post]
walid Lahiani
User offline. Last seen 2 days 7 min ago. Offline
Joined: 6 Nov 2010
Content Credits: 44
Groups: None

Good morning,

I have a scope of work of one project ,

-I extract activities,durations,relationships,I do the WBS,OBS

-Now ,what type of progress I have to choice (physical or unit or or or...)

          what type of duration to choice

 how to do the update every week and where to store the historic (is it in doing many baslines???-every week)

How to update the progress ,is it on updating the ressource units....

How to do the weights...

I know it's many questions at one time ,you can respond to some and not to all :)

 

 

Thank you

          

         

Replies

Dario Rossa
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 3 Feb 2012
Content Credits: 4
Groups: None

Hi,

to store historic data you may consider using financial peridos. You can create a batch of weekly financial periods in a few clicks with the latest releases. Regarding tho other questions, these coices are stricly dependent on the specific project you are managing.

Dario

Raymund de Laza
User offline. Last seen 1 hour 40 min ago. Offline
Joined: 22 Nov 2009
Content Credits: 150

Hi Mr. Walid,

You may need a Private Tutor for all that queries........