Start to finish (SF) Relationship Example

Dear All

Can any help in me in illustrating any practical Example of two activities having Start to Finish Relationship (SF) . I am confusing it with Finish to start (FS).

Regards

Planning Guy

R
ravirg gehlot 👤 Member for 14 years 8 months

Simple example -

 generator ON automatically  ...as  ur light gone  --  Start to Finish ...

 

 

R
Rafael Davila 👤 Member for 22 years 3 months

Photobucket

In the above example you cannot finish providing site security until new security is in place, if Site Security by Owner is delayed the finish of Site Security by Contractor shall be delayed.

It is rare relationships but it might happen.

Best regards,

Rafael