Fixed Units Duration type

No replies
shima memar
User offline. Last seen 12 years 18 weeks ago. Offline
Joined: 10 Dec 2011
Posts: 7
Groups: None

Dear friends

I’m planning for a manufacturing company which manufactures Steel Structures. Here is description of what I should plan:

Column: 200 ton

Stairs:  400 ton

Handrail:  500 ton

I defined the amount of ton as the budgeted Units of resource for the above activities. Should I define duration type as “Fixed Units”  ? and set the calendar to resource calendar? I mean resource dependent activities?