Hello, I'm new to this forum and have used p3 off and on years ago and had some exposure to p5, my background is more toward Project Controls - Cost management rather than scheduling. Here is my issue/question: I was told by the PM not to baseline the schedule (I know, I should have but I didn't, I did as I was specifically requested), that is a topic for another day, however. I am trying to understand the process of the % completes on my resource loaded schedule which all activities are set to duration percent complete. The schedule has roughtly quarter of the activities which have been actualized, but my issue is with the "Summary Totals" of the duration % complete when I select that option in the Group/Sorting. All of the activiites in a group for example will show 0% complete but the Summary Total of those activites will show greater than 0% or some of the activities % completes show a value greater than 0% but the Summary Total of those activiites show 0%. What is causing this and why are they not consistent? Any help is greatly appreciated! Shannon
Replies