Free Float

2 replies [Last post]
Alberto Homedes L...
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 29 Sep 2011
Posts: 4
Groups: None

Hello,

We need to show the free float, but only the free float of the activities, no the free float of the milestones, resume bars etc. We have been trying some things but is not possible for us, Can someone help us?

 

Thanks

Replies

Alberto Homedes L...
User offline. Last seen 7 years 51 weeks ago. Offline
Joined: 29 Sep 2011
Posts: 4
Groups: None

Thanks Ronald

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

Alberto,

 

I suggest that you create a User Defined Field (integer) named Free Float and then use Global Change to copy FF into this field only if the activity meets your particular criteria.  Good luck!