Resource Loading

2 replies [Last post]
Abhishek Choubey
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 13 Nov 2010
Posts: 12
Groups: None

Greetings of the day!!

I am a rookie in P6 and want to explore about resource loading. I have scheduled the activities in P6. I need to assign resources and calculate Earned value.

 

Can anybody enlighten me towards the resource loading and step by step procedure to do it in P6..

 

Regards,

Abhishek

Replies

Abhishek Choubey
User offline. Last seen 11 years 50 weeks ago. Offline
Joined: 13 Nov 2010
Posts: 12
Groups: None

It will be good if you elucidate me with the complete procedure..

Amro Ahmed
User offline. Last seen 2 years 21 weeks ago. Offline
Joined: 5 Jan 2009
Posts: 107

1-From Enterprise  make your resource dictionary

2-Go to activities list then assign resource activity by activity