Performance Percentage Completion ?

7 replies [Last post]
Shah. HB
User offline. Last seen 18 weeks 20 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi

 

Performance percentage completion: On updating the P6 Program of works monthly (Feb 2011 to Mar 2011)overall percentage completion (Performance Pct Complete ) found to be decreased ,is there any reason behind it?

 

Regards

Shahul

Replies

Shah. HB
User offline. Last seen 18 weeks 20 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773

Thanks to all,the issue got resolved 

Regards

Shahul

Daniel Limson
User offline. Last seen 4 years 38 weeks ago. Offline
Joined: 13 Oct 2001
Posts: 318
Groups: None

Shahul,

There is no other way but to check activity by activty and comparing it to your last months report, i am sure you can find anomalies. you can do a quick check by filtering activities completed and activities in progress.

Regards,

Daniel

Kamarul Bahrin H...
User offline. Last seen 20 weeks 1 day ago. Offline
Joined: 15 Aug 2005
Posts: 23

Hi...

try to check, did you attached the baseline and assign baseline ?

tq

Shah. HB
User offline. Last seen 18 weeks 20 hours ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi to all

 

Many thanks for your valued response

@Gary

No new activities are added.Baseline program is cost loaded .Performance percentage is used for measuring actual field progress through feeding physical percentage in to the activities

@Erdem

I agree with your statement .I did the same and increased the activity percentage as they advance over a month time period .In the end I got strange result is that decrease in percentage when compared with last month.

@Andy

Adding new activity too, remains pointless

 

Please advise.

Andy Power
User offline. Last seen 3 years 30 weeks ago. Offline
Joined: 30 Aug 2006
Posts: 43
Groups: None

You must have added new activities or more value in to the programme?

 

At summary level performance % complete is (BCWP * 100) / BAC.

 

Gary Whitehead
User offline. Last seen 4 years 45 weeks ago. Offline

have you added any new activities since last month?

 

how are you measuring % complete?

Erdem Eminol
User offline. Last seen 6 years 34 weeks ago. Offline
Joined: 22 Feb 2007
Posts: 7

Hi Shahul,

Performance percent complete depends on % complete type. Please check there is any change on that fo activities or not.