Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Global change resource dates

1 reply [Last post]
Anthony Peters
User offline. Last seen 6 years 9 weeks ago. Offline
Joined: 5 Apr 2007
Posts: 18
Groups: None

Is there any global change parameters that will align resource start/finish to activity start finish. I have about 300 activities that need alligning and need a quick way to do it. When i tried a global change, it would only affect activities OR activity resource assignments, not a mixture?

Replies

Raymund de Laza
User offline. Last seen 27 weeks 5 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

> make sure that calendar used for the resources is matching with activity calendar.

> make sure that effective date of Resource units and prices is before the start date of the project.

>make sure that resource curve used will distribute resources from the beginning through the end of the duration of the activity.

> Scheudle the project to make sure changes effects.

>Refresh by keying F5.

 

Hope this will help.