**Timely display of planned project percent completions.

5 replies [Last post]
cenk vardar
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 2 Dec 2010
Posts: 7
Groups: None

Is it possible to display planned(or scheduled) percent completions of whole project on a timely basis, like a spreadsheet?

I will appreciate your help.

 

Thanks

Replies

jeoffrey reyes
User offline. Last seen 3 years 40 weeks ago. Offline
Joined: 19 Jun 2008
Posts: 214

you can try also displaying all the columns you needed then just copy and paste it in your spreadsheet.

 

cheers,

Rashid Iqbal
User offline. Last seen 12 years 27 weeks ago. Offline
Joined: 8 Apr 2009
Posts: 16

Cenk,

Go to baseline project, export the manhour data on a weekly/monthly basis to excel. Run a row for commulative manhours and another for the project % completion. Now this is your baseline S-Curve. Plot you actual completion on top of it to show the variance. If any confusions ....send me an email and I will send you an example. Thanks.

cenk vardar
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 2 Dec 2010
Posts: 7
Groups: None

what?

cenk vardar
User offline. Last seen 13 years 15 weeks ago. Offline
Joined: 2 Dec 2010
Posts: 7
Groups: None

Hi Muhammad, thanks for reply...But where exactly is this S-Curve?

 

I guess it is somewhere under "Tracking" and when displaying "Resource Analysis" and showing on bottom layout "Total allocation Profile"???

 if so, I couldn't find it there...Could you pls guide me in details how to locate it?

Muhammad Waseem, PMP
User offline. Last seen 3 years 27 weeks ago. Offline
Joined: 17 Nov 2006
Posts: 14
Groups: None

Goto S-Curve it shows the planned percentages of whole project on timely basis.

 

Regards

Waseem