Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

SCHEDULE VARIANCE LABOUR UNITS

No replies
kumar s
User offline. Last seen 8 years 16 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

dear all

i have finished recording progress for the project.

all the activities are now 100% complete

but due to some updation problem i still have the difference between the actual labour units and budgeted units.

all the activities are resource loaded.

and progress monitoring is done in units % complete.

so now i want to show the schedule variance labour units(budgetedunits-actaul units)as zero for all the activities.

i wanted to change this using the global change instead of going to each activity and updating.

so can anybody please tell me the global change criteria for doing this.

 

thank you