Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

schedule percentage complete

No replies
Chirag Raval
User offline. Last seen 3 years 28 weeks ago. Offline
Joined: 31 Aug 2009
Posts: 14

how can i create a graph of schedule percentage complete, schedule plan & actual together. I have not added any resources yet nor costs in the project. but say, I have information that out of 100 activities 40 activities have started and out of this 40, for example, 10 are completed and rest are ongoing with varied duration percentage complete, as i have updated them by putting duration percentage complete manually. any idea?