Activity Codes Modification Not Allowed

1 reply [Last post]
Izam Zakaria
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
hi guys,

Just recently I want to modify my activity codes, but software replied "you have reached the maximum number allowed for project "This is controlled by admin preference option on the admin menu"

Is it anybody could advise me where I can do setting on admin preference tabs??

Replies

Izam Zakaria
User offline. Last seen 7 years 16 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Issocay, I found it already