Max Units/ Time

2 replies [Last post]
kumar s
User offline. Last seen 8 years 12 weeks ago. Offline
Joined: 26 Jan 2010
Posts: 159

Dera All,

Can any body expain me the use of Max Units/Time Detail in the resources tab.
what role does it have in the resources levelling.

i am noticing that if i change the Max Units/Time then the over allocation is getting levelled.
Please help me to under stand this guys....

Replies

Ali Farhat
User offline. Last seen 13 years 37 weeks ago. Offline
Joined: 22 Oct 2008
Posts: 120
Groups: None
Satishan,
the difference between max and default units/time is the overtime hours a resoruce can work.
Balaji Surendiran
User offline. Last seen 12 years 45 weeks ago. Offline
Joined: 25 May 2004
Posts: 44
Groups: None

Sathishan
Max units/time lists the selected resource’s availability, or the maximum amount of work units the selected resource can perform in a single work period, according to effective date.
Regards,
Balaji