Changing the baseline data in P6

5 replies [Last post]
Balaji Surendiran
User offline. Last seen 7 years 27 weeks ago. Offline
Joined: 25 May 2004
Posts: 44
Groups: None
Do anyone know how to change the baseline data in P6?
Cheers,
Balaji

Replies

Zoltan Palffy
User offline. Last seen 18 hours 5 min ago. Offline
Joined: 13 Jul 2009
Posts: 2022

unattach it from the current schedule and then make the modifications then re-attach it 

Wildan Firmansyah
User offline. Last seen 18 weeks 3 days ago. Offline
Joined: 1 Aug 2016
Posts: 3
Groups: None

Hello,

I just asked about change budget with some additional,

Do anyone know how to change schedule (regarding to budget) on the ongoing schedule? then, what about the progress(percentage) that has been running or paid?

thanks

shekhar gaikwad
User offline. Last seen 6 years 46 weeks ago. Offline
Joined: 27 Dec 2011
Posts: 2
Groups: None

Dear sir,

      At the time of tracking of project, if i want to create my new  base line project in cuurent PERT. For this i am using maintain base line -restore commond but sometime that update start date has came like this form (23-march-11 A). how i can ignore this 'A' in date formate. due to this i cannot edit the project dates.

     Let me know at time of restore how i can avoid the actual 'A' in date formate of new copy of base line.

please suggest me.............

Balaji Surendiran
User offline. Last seen 7 years 27 weeks ago. Offline
Joined: 25 May 2004
Posts: 44
Groups: None
Thanks a lot, Rodel
Rodel Marasigan
User offline. Last seen 2 weeks 1 day ago. Offline
Joined: 25 Oct 2006
Posts: 1516
Balaji,
You need to detach the baseline first before you can modify data of baseline.
Select Project-> Assign Baselines... then remove the baseline that you need to modify then select Project-> Maintain Baselines-> Restore.
Now you can open the restored baseline and modify data.