Planned Percentage

29 replies [Last post]
Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear friends
How can I view the planned percentage in P6.

With regards
Arun.V

Replies

Zoltan Palffy
User offline. Last seen 4 weeks 2 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

planned what ? you need a measuring stick such as dollars or units

suru kadam
User offline. Last seen 4 years 23 weeks ago. Offline
Joined: 2 Feb 2016
Posts: 7
Groups: None
Guyzzz any one can tell me how do I find planned % from the baseline programme or from updated programme confused
Goli Rahmani
User offline. Last seen 7 years 29 weeks ago. Offline
Hi all How can i see percent complete plan and actual for wbs summary? Thanks
Goli Rahmani
User offline. Last seen 7 years 29 weeks ago. Offline
Hi all How can i see percent complete plan and actual for wbs summary? Thanks
Goli Rahmani
User offline. Last seen 7 years 29 weeks ago. Offline
Hi all How can i see percent complete plan and actual for wbs summary? Thanks
Goli Rahmani
User offline. Last seen 7 years 29 weeks ago. Offline
Hi all How can i see percent complete plan and actual for wbs summary? Thanks
Zq qz
User offline. Last seen 12 years 14 weeks ago. Offline
Joined: 6 Jun 2003
Posts: 163
Groups: None
in the activity menu, click column , then find the percent you want in the list.

R. Catalan
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Sitaram,

If your programme is not resource-loaded, you can still show the roll-up summary of Schedule % Complete by assigning expenses to your activities.

And, with the assigned expenses you can do variance analysis by cost (Performance % Complete). But you still have to do tracking your programme by CPM (variance in days) to have the real picture of the current update.

Best regards,

R. Catalan
David Kelly
User offline. Last seen 1 year 38 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Schedule percent complete is based on money at the summary bar level. It will only display a value if:

The activities have resources
Those resources have a unit price.

For those environments that do not use P6 for costing, set all the resources to the same price (e.g. $1.00) and then you will have a percent complete. that matches P3’s summarisation by resource. REmember Schedule % complete is from the baseline (we used to call it "planned percent complete")
Sitaram Sakamuri
User offline. Last seen 4 years 9 weeks ago. Offline
Joined: 27 Sep 2006
Posts: 30
Groups: None
why are we unable to get the schedule % complete on the summary bars. Though the project is completed by 25%, the top summary bar is still showing 0 %complete while the activities are showing correctly. How to rectify it and is there a way to find the summarised % complete just like in P3. If not in P6, is there any way that can be done in excel (means to compute the planned % at various stages of the project). Do reply immediately
Roldan Bartolome
User offline. Last seen 4 years 27 weeks ago. Offline
Joined: 4 Aug 2007
Posts: 14
Arun,

Send me your e-mail add and i’ll send you the percent completion type use in P6.


regards,

roldan
R. Catalan
User offline. Last seen 12 years 8 weeks ago. Offline
Joined: 15 Aug 2005
Posts: 314
Groups: None
Arun,

1) % Complete in P3 (also in Sched Log) = Duration % Complete in P6

2) Autocost Rules "link/unlink remaining duration and schedule % complete in P3 = Physical % Complete in P6

Mustafa,

You have to cost-load your programme in order to roll-up the Schedule % Complete in P5.

Best regards,

R. Catalan
Mustafa Ismayilzada
User offline. Last seen 4 years 37 weeks ago. Offline
Joined: 25 Jun 2007
Posts: 26
Guys,

Could you please let me know how to make % Shedule to be shown in Level 3 in P5?

There is no problem to show the planned progress at activity level, but when you roll it up to let’s say level 3 it gets blank.

Any ideas?

Cheers
Mustafa
Wilfredo Jr. Flores
User offline. Last seen 11 years 51 weeks ago. Offline
Joined: 3 Sep 2005
Posts: 32
Groups: None
hi Arun,

Arnold is right. Actual Values (%) depends on how you will monitor the project. It may be based on cost, material, manpower. About the automatic scheduling, when you run the update progress in P6, it will automatically update all your resources depending on the schedule to get planned %, just like in P3, but it is a long process if you will need the planned % for each month. It is better to assign baseline, then get all planned % for each resources by report writer in P6 either monthly or weekly and fix it in excel. Then just add the actual percentage on every update.

Hope this will help in your planning


regards

Wilfredo


quoting
"Thnxs Arnold
Do we can use this for project planned percentage ..
Before in P3 we were getting this information by scheduling report .At last last it will show like 35.5% som thhing like that .....
We were taking the planned percentage from automatic scheduling ....

Actual percentage from the schedule report of monthly updation manuallyyyy...

I think Arnold nw u can solve my prob very easily in P6

With regards
Arun.V "
Jay S
User offline. Last seen 9 years 40 weeks ago. Offline
Joined: 10 Jun 2008
Posts: 36
% Complete = Actual / Forecast @ Complete.
% earned = Budget (Original / Current x Physical % Complete)

What is required.
Anbin Ponnith
User offline. Last seen 8 years 5 weeks ago. Offline
Joined: 8 Jun 2009
Posts: 158
Dear Arun,

Also how is your client expecting, Duration based % complete or cost based % complete.


I guess you are aware how P3 calculates the Percentage complete displayed in the Schedule log.

If you need the same %complete you can try it using global change.




With Thanks & Regards,

Anbin Ponnith
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

As I have mentioned in my previous post #7, you cannot find the % complete in schedule log of P6 as what you can see in P3.

If you wish to check the log, go to Tools --> Schedule, select "View Log". Make sure you tick the "Log to file" and locate the SchedLog.txt

Regards,

Arnold


Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
In p3 --- Tools ----- Schedule----Schedule now --- view on screen----There we can see a report .In that report @ the end it is progress percentage ..
Could I get that percentage in P6

Regards
Arun
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

What type of % complete that your Manager ask you? When you trying to present your % complete, it is based on what?

1. Duration (Time)
2. Units (Quantity or any resources you assign to your activities)
3. Physical - User’s manually input or based on activity steps.

Regards,

Arnold
Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Hai Arnold
I not getting u ...

For example
U sheduled a program .After one month ur manager is asking that How much percentage of the project is completed ??

How u will find in P6????

With regards
Arun.V
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

You can calculate your % complete using the three different types of "% complete type".

1. Duration
2. Physical
3. Units

Regards,

Arnold
Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Oh God
Thn How we can calculatee the project progress percentage ???

Regards
Arun.V
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

You mean in Schedule Log? Unfortunately, there is no overall % complete shown in the schedule log.

You can show the overall % complete in the column at Activities and WBS windows.

Regards,

Arnold

Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
No arnold
Before in P3
While we updating a percentage from the schedule log
like 37.5 % completed some thing like ...

Can we see the over all project progress percentage from P6 This is my question???

Regards
Arun
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

You can have your Planned % when you assign a baseline to your current project, and actual % depends on how you monitor your project. (e.g. based on quantity, cost, man-day, man-hour and etc.).

Regards,

Arnold
Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Dear Arnold

Could u tell me how to find the Project Planned & Actual percentage over all????

With regards
Arun.V
Arun Vasanth
User offline. Last seen 5 years 7 weeks ago. Offline
Joined: 12 Oct 2009
Posts: 200
Groups: GPC Qatar
Thnxs Arnold
Do we can use this for project planned percentage ..
Before in P3 we were getting this information by scheduling report .At last last it will show like 35.5% som thhing like that .....
We were taking the planned percentage from automatic scheduling ....

Actual percentage from the schedule report of monthly updation manuallyyyy...

I think Arnold nw u can solve my prob very easily in P6

With regards
Arun.V
Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Arun,

Go to View Menu --> Columns --> expand the Percent Completes and look for Schedule % Complete (Planned % Complete) then double click select OK.

Regards,

Arnold
Anujkumar Mishra
User offline. Last seen 4 years 13 weeks ago. Offline
Joined: 16 Sep 2008
Posts: 9
Dear Roldan,
Kindly send me percent completion type used in P6 at anuj.2121@gmail.com.

Regards,
Anuj