Group Totals not matching duration

3 replies [Last post]
Scott McCarthy-Pu...
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 16 Feb 2007
Posts: 5
I’m having real difficulties with this.

For example, I have 5 activities in a group, the total duration from start to finish is 10 days and one hour, yet the Group Total shows 4days and 4 hours??

I have all the activities on the same calander....

??

HELP!

Cheers,
Scott.

Replies

Scott McCarthy-Pu...
User offline. Last seen 12 years 49 weeks ago. Offline
Joined: 16 Feb 2007
Posts: 5
Thanks Muhammad!

Great fix!

Scott.

muhammad anwar
User offline. Last seen 3 years 36 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Scott,

The Duration in Group band(summary duration) is calculated from Global default calendar and unit of time admin preference(ie 8h/d or 10/d). It starts from the earliest time in the group of activities. If hrs/day in user preference and default duration in admin preference are same as well as default Global calendar is same as activities calendar then you should not experience this problem.

regards

M
muhammad anwar
User offline. Last seen 3 years 36 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Scott,

The Duration in Group band(summary duration) is calculated from Global default calendar and unit of time admin preference(ie 8h/d or 10/d). It starts from the earliest time in the group of activities. If hrs/day in user preference and default duration in admin preference are same as well as default Global calendar is same as activities calendar then you should not experience this problem.

regards

M