BUDGET UNITS OVERRIDE ACTUAL UNITS W/ACTUAL FINISH

5 replies [Last post]
JEREMY CORNER
User offline. Last seen 9 years 38 weeks ago. Offline
Joined: 26 Oct 2009
Posts: 5
Groups: None
HOW DO I STOP THE BUDGETED UNITS FROM OVERRIDING THE ACTUAL UNITS THAT ARE APPLIED TO AN ACTIVITY? ONLY HAPPENS WHEN I APPLY AN ACTUAL FINISH.

Replies

David Kelly
User offline. Last seen 4 days 37 min ago. Offline
Joined: 19 Oct 2004
Posts: 560
Jeremy,

I probably have more experience than all of them put together! And that goes for quite a few guys on this forum.

JEREMY CORNER
User offline. Last seen 9 years 38 weeks ago. Offline
Joined: 26 Oct 2009
Posts: 5
Groups: None
Thanks - You’ve done what our Primavera Rep. and Primavera help line could not do. That was very frustrating for our guys in the field and for me. -Rookie eh-
JC
David Kelly
User offline. Last seen 4 days 37 min ago. Offline
Joined: 19 Oct 2004
Posts: 560

Set the activity to "auto compute actuals"

Set the resource to "auto compute actuals"


and there is another one, but I am having a "senior moment", I shall fire P6 up and refresh
JEREMY CORNER
User offline. Last seen 9 years 38 weeks ago. Offline
Joined: 26 Oct 2009
Posts: 5
Groups: None
David - Thank you. When you say loads of other ways, How else can it be done?
Thanks again
JC
David Kelly
User offline. Last seen 4 days 37 min ago. Offline
Joined: 19 Oct 2004
Posts: 560
Loads of places you can make it do that!!!!

In the project tab, check under the "Calculations" tab that "recalculate actual unist an cost when duration % complete changes" is NOT checked.