Date,Gap,Completion ...and so on.....

2 replies [Last post]
Izam Zakaria
User offline. Last seen 7 years 20 weeks ago. Offline
Joined: 28 May 2006
Posts: 221
Gents,

Just wanna to ask you all guys, recently I received one schedule in .xer & .plf format but once I import it to my P6 the completion date have a gap around three days if compared with the original one. I’ve been checked on “Dates Tab – Planned & Data dates” all of them are totally identical but still have a gap. How come this happen is it because the version of p6? I’m currently use 6.2 and my main cont. using 6.0.

Replies

muhammad anwar
User offline. Last seen 3 years 41 weeks ago. Offline
Joined: 5 Feb 2007
Posts: 46
Groups: TILOS
Izam,


It seems to me you have problem with your calender. when you import from XER file. The default configuration for import options have keep existing calendars. This mean if you have same name for the calender in your existing database then it will not update the calender. What you need to do is match the holidays for both calenders or while importing you can change this option in configuration but be aware for the later option, it will happen to all those projects which have assigned that calender assigned.


Hope this will help

regads

Muhammad
MNT .
User offline. Last seen 12 years 47 weeks ago. Offline
Joined: 6 Oct 2009
Posts: 15
Dear Izam ,

During importing theres an option to schedule the project after import; it should be unchecked.


Regards,

Alex!