Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Bearing Negative Total Float if Apply Must Finish date

3 replies [Last post]
Cecil Soliva
User offline. Last seen 6 years 32 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20
Hi Planners:

I made a project having an early finish date of October 15, 2010 and the same I provided to the project details must be finished on October 15, 2010. I found out that the Total Float of the critical Path changes from 0 to -1. How does P6 reads with this regards?


Thank you,

Cecil

Replies

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147

You are welcome.

Cecil Soliva
User offline. Last seen 6 years 32 weeks ago. Offline
Joined: 17 Apr 2004
Posts: 20

Thanks again Arnold..I’ve wasted a lot of time, thinking how it became -1 TF..


regards,

Cecil

Arnold Puy
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cecil,

Try to check the finish date.

1. Go to Edit --> User Preferences --> Dates tab, Time, tick Show minutes and select the 12 hour (1:30 PM).
2. Go to Enterprise --> Projects
2. In Projects Detail Tab --> Dates
3. In "Must Finish Date" if you notice the the time is 12:00 AM, change this to 4:00PM or 5:00PM. It depends on the calendar and time you use.

Otherwise, check your finish date. It should be the same with "Must Finish Date especially the time.

Regards,

Arnold