project percent complet

10 replies [Last post]
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388

I read that there is a workaround to let P6 calculate the total percent complete of schedule when activities are using physical percent complete.

any idea !!

Replies

warren sika
User offline. Last seen 4 years 42 weeks ago. Offline
Joined: 9 Jan 2013
Posts: 24
Groups: GPC Qatar

In P3, you will get details of the project such as the following:

Number of activities, Number of activities in longest path, Started activities, Completed activities, Number of relationships  and Percent complete.     

What I am after for is the "Percent Complete".  My question is, in P6 how will I know its Percent Complete?  Thanks. Warren
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
Ahmed, that what i want to say, but in mimoune’s english ;)

thanks very much
Shahzad Ahmad
User offline. Last seen 14 years 39 weeks ago. Offline
Joined: 14 Feb 2008
Posts: 96
Hi Mimoune

Performance % complete related to cost means price per unit

if your resource assign only unit...not the cost

then Performance % Complete will not help.

Shahzad
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
thanks Alex;

of course the resource must have unit/price assigned, otherwise performance % complete will show always 0
and to use manhour as a weight factor, we just put price as 1



mimoune

note to myself: read the manual before asking questions
James Shimmon
User offline. Last seen 13 years 29 weeks ago. Offline
Joined: 12 Jan 2007
Posts: 93
Mimoune
Call up a column called performance % complete, this should mirror physical % complete and will roll up through the WBS levels
Cheers

Shimmo
mimoune djouallah
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 14 Oct 2006
Posts: 388
hi alex, yes it is ;)

thanks in advance
Alex Wong
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS

Hi

Depends on whether your schedule is resource loaded

Regards

Alex
Shanmugam Thangam...
User offline. Last seen 3 years 42 weeks ago. Offline
Joined: 3 Feb 2005
Posts: 24
Groups: None
Is there any possible way to show project % complete in terms of time / effort like in P3?

Regards,

Shan
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Shanmugam,

In terms of time, you can use "duration % complete".

Regards.



Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Mimoune,

I agree with James, to roll up the percentage based on physical you need to have your performnance % complete equal to your physical % complete. Then, try to change your "% complete type" from duration to physical and observe what will be the outcome.

This will only work if your programme is cost loaded.

Just try this exercise and let us know.

Hope this helps.

Regards,

Arnold