Original Dur Vs Remaining Dur

3 replies [Last post]
Mohsen M
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 10 Mar 2008
Posts: 18
Groups: None
Hello PP Friends,

I have two projects imported form MSP into P6. The problem is this, when I change the original duration of activities that are scheduled to start in the future the remaining duration does not change accordingly. From the “Projects” view and under “Calculations” tab I have “Reset remaining duration and units to original” selected. Can anyone help with that please?

Cheers,

Mohsen

Replies

Mohsen M
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 10 Mar 2008
Posts: 18
Groups: None
Hi David & Dieter,

Thank you for your help with this matter. It’s all good now.

Cheers,

Mohsen
Dieter Wambach
User offline. Last seen 6 years 51 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Mohsen
... and "Link budget and..."? Did you recalculate?

Regards
Dieter
David Kelly
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Check "link budget and at completion for not started activities" in the calculations tab.....