P6 Calculating Earned Value

1 reply [Last post]
Omar Grant
User offline. Last seen 9 years 10 weeks ago. Offline
Joined: 25 Sep 2005
Posts: 71
I have a schedule with resources applied to activities with percentage type = physical. I also have weighted steps on each activity. When I update the steps I get a calculated % complete against the activity OK but, unless the activity steps are all 100% I do not get a value for Earned Value Labour Units. I have checked all the preferences & calculation tabs to no avail. Can anyone help please?

Replies

Anoon Iimos
User offline. Last seen 2 years 6 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1169
Omar,

Physical % progress is manually calculated (or you input manually) so you need to calculate earned value manually as well.