Problem Grouping & Sorting P6 xer I have imported

2 replies [Last post]
Christopher Nicolas
User offline. Last seen 14 years 51 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
Hi all - I have imported an xer which is quite large, about 6mb. Anyway when I group and sort as per the organisation the contractor has provided me, the programme organises to all but one of the activity codes (floor level). As such I can’t look at the programme in the format I want. Is there any reason why this has happened? I know I have used ’floor level’ for my own projects in P6 but that has been a project grouping.

I note that the imported activity codes are all under global.

Any help is appreciated

Replies

Christopher Nicolas
User offline. Last seen 14 years 51 weeks ago. Offline
Joined: 22 May 2006
Posts: 24
Groups: None
Hey Arnold - it wasn’t the indent - something else that I figured out - cheers again for your help.
Arnold Puy
User offline. Last seen 9 years 8 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Chris,

Try to uncheck the Indent box under the Group & Sort and select the required codes under the Group by.