Negative Lag (Here We Go Again) HELP!!!

1 reply [Last post]
Benjamin Mora
User offline. Last seen 10 years 36 weeks ago. Offline
Joined: 19 Oct 2007
Posts: 66
Groups: None
I know there have been several threads on the use of negative lag, but I am looking for an alternative. I have to schedule a Red Zone meeting 60 days prior to the completion of certain phases of work.

Now, I know I can, in the initial schedule, setup a relationship with an activity that lands on the date that the meeting supposed to happen, but risk that a delay would push that date out even though it should not delay the meeting.

How can I get around this and not use negative lag with living schedule?

Thanks for your help.

Replies

Paul Silver
User offline. Last seen 5 years 1 week ago. Offline
Joined: 30 Sep 2004
Posts: 16
Benjamin,

Try applying the primary constraint "as late as possible" to the Meeting Notification activity with FS60 lag to the successor activity, ie. the appropriate Completion Milestone.
If your completion date moves, (earlier or later) the Meeting Notification activity will move correspondingly.

Regards

Paul Silver