EDITING ACTID Column in PREDECCESSOR BOX-P6

1 reply [Last post]
Waseem Saber
User offline. Last seen 1 year 33 weeks ago. Offline
Joined: 1 Dec 2004
Posts: 63
Groups: None
i am not able to edit the ACTID column in the predecessor box, this was possible in P5, i was able to cut & Paste the ActID’s, this was a very handy way to get the linking of relationship quickly... is this a problem curable? are there any similar concerns, lets share it,please.......



regards

waseem saber

Replies

Salahuddin Ahmed
User offline. Last seen 7 years 50 weeks ago. Offline
Joined: 1 Apr 2008
Posts: 25
Groups: None
Waseem,

Well what I understand is you are asking how to edit Activity ID in predecdssor box.

> Click on activity where you want changes
> Open activity detail
> Double click on ACT ID
> Edit as required

Thanks

Salah