When resch’ my Baseline milestones move along

1 reply [Last post]
Joel Gilbert
User offline. Last seen 4 years 22 weeks ago. Offline
Joined: 5 May 2003
Posts: 166
This may have been dealt before,But I dont have time to read through all the Forums.

I’ve baselined my programm, now I update it, then I reschedule and I see my activities baseline dates stay as baselined but my milestones dont. they move along with the re-scheduled dates. What am I doing wrong? is there a way of saving the baseline. Note I am working on a 54 projects portfolio.

Any quick help welcomed.

Replies

Dieter Wambach
User offline. Last seen 6 years 48 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Joel
Which timescale you selected for the baseline ms?
It must be Primary Baseline, maybe you selected remaining.
Cheers
Dieter