Copy WBS structure to Activity code

3 replies [Last post]
K D
User offline. Last seen 15 years 24 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi all,
Our company need to apply a new WBS structure, but we want to get back the old structure in some case. So we create a activity code system which identical to WBS structure. In future if we want to get back, simple group to Activity code.
But our WBS structure is really huge. Can anyone give an idea how to copy WBS structure to Activity code fastly? Currently I’m doing copy manually. Very slow.

Regards

Replies

Hemanth Kumar
User offline. Last seen 39 weeks 3 days ago. Offline
Joined: 1 Nov 2002
Posts: 260
Groups: None
Great Idea
Thanks mate
K D
User offline. Last seen 15 years 24 weeks ago. Offline
Joined: 25 Sep 2007
Posts: 247
Groups: None
Hi david
Thanks for your solution.
I’m gonna try it. It sound very cool.
Thanks
David Kelly
User offline. Last seen 1 year 34 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
You can use p3 3.1 as an intermediary. Export to P3 3.1, then when you import you can select to import the WBS as an activity code