Copying Codes in P5

2 replies [Last post]
Kevin Matthews
User offline. Last seen 14 years 10 weeks ago. Offline
Joined: 21 Jun 2006
Posts: 57
G’day,

In P3 you can copy and paste codes between activities, which is a great time saving task. In P5 you need to change each activity individually. Is there a way to bulk copy codes between activities ?

Keep Planning,

Kevin.

Replies

Kevin Matthews
User offline. Last seen 14 years 10 weeks ago. Offline
Joined: 21 Jun 2006
Posts: 57
Thanks again Dieter,

Keep planning,

Kevin.
Dieter Wambach
User offline. Last seen 6 years 49 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Hi Kevin
In P5 it’s much easier to assign codes than in 3.1.
On the right side of the screen there are some icons, Number 4 from below is "Assign Activity Codes". Now you can select groups of activities and assign codes to them - or remove codes from them.
"Fill Down" works very similiar to P3 3.1.
Regards
Dieter