Stored Period Performance

1 reply [Last post]
Robin Kilmister
User offline. Last seen 12 years 24 weeks ago. Offline
Joined: 19 Apr 2007
Posts: 10
Groups: None
Hello Planners,

I am transferring my projects from my local PMDB to a central server based PMDB.
I have noticed that all of my previous ’stored period performances’ have been rolled up into one overall ’actual labour units’ value.
Is there a way to extract the previously ’stored period performance’ information as loggeed on the local PMDB in the newly imported central server PMDB project?

Many thanks for your assistance.

Robin.

Replies

Steve Barker
User offline. Last seen 16 years 41 weeks ago. Offline
Joined: 14 Jul 2004
Posts: 5
prim21683

If you have access to the Primavera Knowledge base, give this a try. You may have it defined differently in the databases you are trying to import to.