Re: Exporting BCWS and BCWP?

2 replies [Last post]
Kenny Holmes
User offline. Last seen 16 years 42 weeks ago. Offline
Joined: 3 Jun 2007
Posts: 9
Groups: None
Hi All

Finally getting the hang of this P3e applicatiion! Can anyone help and put me on the path to exporting Timephased BCWP + BCWS to a csv file? I know how to export etc however I am having paticular problems with these 2 items (I have been a junior planner for a month and its the first time I have been asked for this information.


Thanks in advance :0)

Replies

Kenny Holmes
User offline. Last seen 16 years 42 weeks ago. Offline
Joined: 3 Jun 2007
Posts: 9
Groups: None
Thanks, figured it out today :0) realised all fields are available however you need to look for them! Thanks again!
Niek Zonneveld
User offline. Last seen 2 years 2 weeks ago. Offline
Joined: 17 Mar 2005
Posts: 188
Groups: None
Kenny,

You’ll need to export that data through a report.

Just generate a report with the wizard - choose time distributed data and select activities as subject area - select the earned value fields you want print and the interval size, and generate ASCII output with the delimiter you desire.

HTH