Resources on LOE Activities

2 replies [Last post]
Matthew Lovkis
User offline. Last seen 16 years 21 weeks ago. Offline
Joined: 26 Nov 2006
Posts: 19
Groups: None
Hi All,

I’m going nuts with my schedule at the moment!

I am updating resource allocations at the moment and after I spent a long time updating the resources on my Level of Effort activities, I scheduled the project, AND all of the hours changed on the L.O.E. activities.

How can I prevent this from happening?

I want to be able to regularly update hours associated with a Level of Effort activity. And once I press F9 I don’t want the hours to change.

Thanks a lot,

Matt Lovkis

Replies

Matthew Lovkis
User offline. Last seen 16 years 21 weeks ago. Offline
Joined: 26 Nov 2006
Posts: 19
Groups: None
Thanks tonnes mate,

That was the one!

It was the recalculate toggle that needed to be unchecked.

Cheers,

Matt Lovkis
Karim Mounir
User offline. Last seen 9 years 36 weeks ago. Offline
Joined: 5 Apr 2006
Posts: 314
Groups: None
Hi,
U can check the post titled "Applying Progress To A Level Of Effort Activity" in p3 e/c forum.