Critical Path

1 reply [Last post]
Davie Ross
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 7 Aug 2006
Posts: 10
Groups: None
Can anyone tell me if you can show critical path in summary bars?

Replies

Sufian Malik
User offline. Last seen 17 years 7 weeks ago. Offline
Joined: 24 Nov 2006
Posts: 15
Groups: None
Hi Dave

The summary bar is a display of all of the activities within that band....how about rolling up critical activities so they are displayed on the summary bar?

1) Right click on the gantt chart and select Bars
2) From the list of bars select Critical Remaining
3) Click on the Bar Settings tab and confirm there’s a tick next to ’Show Bar When Collapsed’
4) When you collapse all of the bars - the summary bar will now display the critical red activities on top (Click on the Layout Options Bar and select Collapse All, Expand as appropriate)

Hope that helps

Sufian