Im porting mpx, mpp to P5

2 replies [Last post]
Hady Shendy, PMP
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 11 Jun 2006
Posts: 34
Groups: None
I use WBS Chart Pro from www.criticaltools.com to create the WBS on simply way
Then I do 2 ways of out put:
1- Save as MPX file, or
2-automatically open MS Project then save it MPP files

Try to import any of these files to P5; I have the same problem as below:
* Each WBS level represent as WBS level, it’s OK!
*but also represent it as an activity also
And as we knew the activities are the last level on WBS

As a prof. project manager you need to create WBS 1st then you go to network diagram, therefore believe me the upper program is the right tool for that
Please advice

Replies

Marcio Sampaio
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Just do a filter showing activity type = WBS summary and delete all.

Regards.
Hady Shendy, PMP
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 11 Jun 2006
Posts: 34
Groups: None
Importing mpp to p5
when import mmp files to primavera p5, the summary tasks become activities plus it’s character as WBS level

please advise to keep the summary tasks on MSP as a WBS level with imported into P5

Thanks