Add Actual to Remaining

1 reply [Last post]
Marcio Sampaio
User offline. Last seen 11 years 30 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
Dear PP friends,

Do u know when i use the option "Add Actual to Remainig" on Project Calculations??

Best regards,

Marcio Eduardo
Rio de Janeiro - Brazil

Replies

Marcio Sampaio
User offline. Last seen 11 years 30 weeks ago. Offline
Joined: 7 Nov 2005
Posts: 658
I normaly use "Subtract Actual from At Completion".